Brown Ave. and Well No. 2 Improvements – Work Completed in 2021
GM Contracting was a general contractor on this project. The project consisted of installing approx. 3000LF of 16” watermain via trenchless and open cut methods. Street work and connections were also included as part of this project.
SW Area Street and Utility Improvements – Work Completed in 2021
GM Contracting was a general contractor on this project. Work consisted of installing new utilities and streets on approx. 20 blocks in an area of town.
Fairlakes Ave. Street and Utility Improvement – Work complete 2021
GM Contracting was a general contractor on this project. Work consisted of installing new utilities and streets on approx. 3 blocks.
South Area Utility Extension – Work completed in 2021
GM Contracting was a general contractor on this project. The project consisted of installing approx. 8000LF of 14” – 16” pipe via directional drilling. Some open cut pipe installation, connections, and air release manholes also went along with this project.
Well No. 5 Raw Watermain – Work Completed in 2021
GM Contracting was a general contractor on this project. The project consisted of installing approx. 6000lf of 12” watermain by both trenchless and open cut methods. Casing pipes and connections were also included as part of this project.
Twin Lakes Low Pressure Sewer – work completed in 2021
GM Contracting was a general contractor on this project. The project consisted of installing approx. 15000lf of a sewer forcemain via directional drilling. Connections, air release manholes, and cleanouts also went along with this project.
Covington Road Watermain Looping Work completed in 2021
GM Contracting was a general contractor on this project. The project consists of pipe bursting approx. 800LF of 12” DIP pipe along with connections and services.
2020 Sanitary Sewer Improvement – Work Completed in 2021
GM Contracting was a general contractor on this project. The project consisted of installing new sanitary sewer and streets on approx. 16 blocks in town.
2019 Polk County WMR Contract 1
GM Contracting was a general contractor on this project which consisted of approx. 4500LF of 8-12” watermain installed via directional drilling. Connections and services were also included as part of this project.
2019 Main Street Watermain Improvements
GM Contracting was a general contractor on this project which consisted of approx. 2000LF of 12” PVC and DIP watermain installed via directional drilling. Connections and services were also included as part of this project.
2019 Oak Ridge Road Water Main
GM Contracting was a general contractor on this project which consisted of pipe bursting approx. 400ft of an 8” Ductile pipe with 10” HDPE. Connections were made on each end along with services.
2019 San Sew Repair
GM Contracting was a general contractor on this project which consisted of pipe bursting approx. 550LF of a 12” sewer main with 12” HDPE. Services and manhole connections were also included on this project.
2018 Sixth Street SW Improvements
GM Contracting was the general contractor on this project which consisted of approx. 8 blocks of reconstruct. All utilities, sewer, water, storm sewer, were replaced and the streets rebuilt. Project took approx. 6 months.
2018 Street Improvements
GM Contracting was the general contractor on this project which consisted of approx. 5 blocks of reconstruct. All utilities were replaced, and the streets rebuilt. Project took approx. 4 months.
2018 Adams Street Phase 2
GM Contracting was the general contractor on this project which consisted of approx. 2500LF of 24” sewer pipe 20 ft deep and 2500LF of 12” watermain. Connections and manholes were also installed on this project. Project took approx. 2 months.
2018 10th Street
GM Contracting was a subcontractor on this project, hired by the general contractor to conduct the pipe bursting needed. Approx. 1700LF of a 10” sewer line was installed via pipe bursting. Connections, manholes, and services were also included as part of GM Contractings scope.
2017-2018 Commercial Park
GM Contracting was the general contractor on this project which consisted of installing infrastructure for a new industrial park for the city. Sewer, water, and storm sewer was installed along with site grading and building roads. Project took approx. 1 year.
2017 East Main Street Utility Reconstruction
GM Contracting was a general contractor on this project which consisted of installing approx. 1500LF of 10” watermain via pipe bursting. Connections and services were also included as part of this project.
Sanitary Sewer System Improvements Work Completed in 2016-2017
GM Contracting was the general contractor on this project. The project consisted of 3200LF of 10” forcemain directional drilled, the installation of a new lift station, and modifications to an existing lift station.
2016 Lift Station Work Completed 2018
GM Contracting was the general contractor on this project. The project consisted of the installation of a new lift station and approx. 500LF of a 12” sanitary sewer.
Westwood Court Lift Station Work Completed in 2016
GM Contracting was the general contractor on this project. This project consisted of 1500LF of 10” – 15” gravity sewer open cut, 2100LF of 6” forcemain, and a new lift station.
Kamp Dels Lift Station Work Completed in 2015
GM Contracting was the general contractor on this project. The project consisted of the installation of a new lift station and approx .1200LF of forcemain.
2015 Raw Watermain Pipe Bursting
GM Contracting was the general contractor on this project which consisted of approx. 7000LF of 16” watermain installed via pipe bursting. This project also included connections and valve vault reconstruction.
City of Lakefield – 2014 Street Improvements
City of West Des Moines IA – 2014 Water Main Replacement
City of Sherburn – 2014 Street Improvements
City of Milford IA – 2013 Polaris Lift Station
CITY OF ZIMMERMAN – 2012 FREMONT AVE WATERMAIN IMPROVEMENTS
CITY OF BUTTERFIELD – 2012 FORCEMAIN REPLACEMENT
CITY OF LAKEFIELD – 2012 STREET IMPROVEMENTS
CITY OF FOREST CITY IA – 2011 SANITARY SEWER EXTENSION
City of Dayton IA – 2010 Water Main Improvements
City of Ormsby – 2010 Sewer Improvements
City of Wilmont – 2010 Water Main Improvements
City of Rockford – TH 55 Sanitary Sewer & Watermain Improvements
City of Nicollet – Nicollet Street & Alley
City of St James – Storm Sewer Improvements
City of Garfield – Sanitary Forcemain & Lift Station
City of Spirit Lake IA – East Lake Industrial Park
City of Wells – CSAH 62 Reconstruction
City of Litchfield – Sanitary Sewer Improvements
City of Minnetrista – County Road 151 & 19 Trunk Watermain
City of Elk River – Twin Lake Road Watermain
City of Lake Elmo – Lake Elmo Avenue Watermain Improvements
CITY OF LAKE CRYSTAL – INDUSTRIAL PARK LIFT STATION PROJECT
CITY OF ORONO
CITY OF ALGONA IA – NEW WATER MAIN – GARFIELD & CHURCH ST
CITY OF FRIDLEY
City of Coon Rapids
City of Eagle Lake – 2nd & 3rd Street and Parkway Ave Improvements
City of Marshall – TH 59/Ontario Drive
City of Plymouth – Four Seasons Mall – Raw Watermain
City of Kandiyohi – Sanitary Sewer – Wastewater Regionalization with GLSSWD
City of Roseville – Watermain Replacement – Churchill St & Oxford St
City of Harrisburg SD – Phase II Force Main
Grant Street Watermain Improvements
GM Contracting was a subcontractor on this project. GM Contracting’s portion of this project included pipe bursting approx. 400LF of 6” watermain