Projects

Brown Ave. and Well No. 2 Improvements – Work Completed in 2021

GM Contracting was a general contractor on this project.  The project consisted of installing approx. 3000LF of 16” watermain via trenchless and open cut methods.  Street work and connections were also included as part of this project.

Location: City of Waseca

SW Area Street and Utility Improvements – Work Completed in 2021

GM Contracting was a general contractor on this project.  Work consisted of installing new utilities and streets on approx. 20 blocks in an area of town.

Location: City of Lake Crystal

Fairlakes Ave. Street and Utility Improvement – Work complete 2021

GM Contracting was a general contractor on this project.  Work consisted of installing new utilities and streets on approx. 3 blocks.

Location: City of Fairmont

South Area Utility Extension – Work completed in 2021

GM Contracting was a general contractor on this project.  The project consisted of installing approx. 8000LF of 14” – 16” pipe via directional drilling.  Some open cut pipe installation, connections, and air release manholes also went along with this project.

Location: City of Victoria, MN

Well No. 5 Raw Watermain – Work Completed in 2021

GM Contracting was a general contractor on this project.  The project consisted of installing approx. 6000lf of 12” watermain by both trenchless and open cut methods.  Casing pipes and connections were also included as part of this project.

Location: City of Pipestone, MN

Twin Lakes Low Pressure Sewer – work completed in 2021

GM Contracting was a general contractor on this project.  The project consisted of installing approx. 15000lf of a sewer forcemain via directional drilling.  Connections, air release manholes, and cleanouts also went along with this project.

Location: Calhoun County, IA

Covington Road Watermain Looping Work completed in 2021

GM Contracting was a general contractor on this project.  The project consists of pipe bursting approx. 800LF of 12” DIP pipe along with connections and services.

Location: City of Shorewood, MN

2020 Sanitary Sewer Improvement – Work Completed in 2021

GM Contracting was a general contractor on this project.  The project consisted of installing new sanitary sewer and streets on approx. 16 blocks in town.

Location: City of Henderson, MN

2019 Polk County WMR Contract 1

GM Contracting was a general contractor on this project which consisted of approx. 4500LF of 8-12” watermain installed via directional drilling.  Connections and services were also included as part of this project.

Location: City of Des Moines, IA

2019 Main Street Watermain Improvements

GM Contracting was a general contractor on this project which consisted of approx. 2000LF of 12” PVC and DIP watermain installed via directional drilling.  Connections and services were also included as part of this project.

Location: City of Algona, IA

2019 Oak Ridge Road Water Main

GM Contracting was a general contractor on this project which consisted of pipe bursting approx. 400ft of an 8” Ductile pipe with 10” HDPE.  Connections were made on each end along with services.

Location: City of Minnetonka, MN

2019 San Sew Repair

GM Contracting was a general contractor on this project which consisted of pipe bursting approx. 550LF of a 12” sewer main with 12” HDPE.  Services and manhole connections were also included on this project.

Location: City of Fulda, MN

2018 Sixth Street SW Improvements

GM Contracting was the general contractor on this project which consisted of approx. 8 blocks of reconstruct.  All utilities, sewer, water, storm sewer, were replaced and the streets rebuilt.  Project took approx. 6 months.

Location: City of Wells, MN

2018 Street Improvements

GM Contracting was the general contractor on this project which consisted of approx. 5 blocks of reconstruct.  All utilities were replaced, and the streets rebuilt.  Project took approx. 4 months.

Location: City of Lakefield, MN

2018 Adams Street Phase 2

GM Contracting was the general contractor on this project which consisted of approx. 2500LF of 24” sewer pipe 20 ft deep and 2500LF of 12” watermain.  Connections and manholes were also installed on this project.  Project took approx. 2 months.

Location: City of Mankato, MN

2018 10th Street

GM Contracting was a subcontractor on this project, hired by the general contractor to conduct the pipe bursting needed.  Approx. 1700LF of a 10” sewer line was installed via pipe bursting.  Connections, manholes, and services were also included as part of GM Contractings scope.

Location: City of Gaylord, MN

2017-2018 Commercial Park

GM Contracting was the general contractor on this project which consisted of installing infrastructure for a new industrial park for the city.  Sewer, water, and storm sewer was installed along with site grading and building roads.  Project took approx. 1 year.

Location: City of Mountain Lake, MN

2017 East Main Street Utility Reconstruction

GM Contracting was a general contractor on this project which consisted of installing approx. 1500LF of 10” watermain via pipe bursting.  Connections and services were also included as part of this project.

Location: City of Anoka, MN

Sanitary Sewer System Improvements Work Completed in 2016-2017

GM Contracting was the general contractor on this project.  The project consisted of 3200LF of 10” forcemain directional drilled, the installation of a new lift station, and modifications to an existing lift station.

Location: City of Chariton, IA

2016 Lift Station Work Completed 2018

GM Contracting was the general contractor on this project.  The project consisted of the installation of a new lift station and approx. 500LF of a 12” sanitary sewer.

Location: Duncombe, IA

Westwood Court Lift Station Work Completed in 2016

GM Contracting was the general contractor on this project.  This project consisted of 1500LF of 10” – 15” gravity sewer open cut, 2100LF of 6” forcemain, and a new lift station.

 

Location: City of Willmar, MN

Kamp Dels Lift Station Work Completed in 2015

GM Contracting was the general contractor on this project.  The project consisted of the installation of a new lift station and approx .1200LF of forcemain.

Location: City of Waterville, MN

2015 Raw Watermain Pipe Bursting

GM Contracting was the general contractor on this project which consisted of approx. 7000LF of 16” watermain installed via pipe bursting.  This project also included connections and valve vault reconstruction.

Location: City of Montevideo, MN

City of Lakefield – 2014 Street Improvements

GM Contracting was a subcontractor on this project which consisted of pipe bursting approx 400 LF of 12″ sanitary sewer.
Location: Lakefield

City of West Des Moines IA – 2014 Water Main Replacement

Installed approx 1,900 LF of directional drilled 8″ watermain with connections to existing watermain.
Location: West Des Moines

City of Sherburn – 2014 Street Improvements

Installed approx 2,900 LF of RCP storm sewer, 4,700 LF of sanitary sewer, 3,100 LF of PVC watermain and 1,100 LF of directionally drilled 8″ sanitary sewer and 6″ watermain. New water and sewer services were also included in this project along with full street reconstruction.
Location: Sherburn

City of Milford IA – 2013 Polaris Lift Station

Installation of lift station, connections to existing sanitary sewer and trenchless sewer pipe installation of 4″ HDPE pipe.
Location: Milford IA

CITY OF ZIMMERMAN – 2012 FREMONT AVE WATERMAIN IMPROVEMENTS

This was a water main project that GM Contracting, Inc. was a general contractor on. It consisted of approx. 3,400 LF of 8″ water main replacement via trenchless methods.
Location: City of Zimmerman

CITY OF BUTTERFIELD – 2012 FORCEMAIN REPLACEMENT

GM Contracting, Inc. was the general contractor on this project. The project consisted of approx. 4,300 LFof open cut and directional drill 8″ forcemain with valve replacement at waste water treatment facility.
Location: City of Butterfield

CITY OF LAKEFIELD – 2012 STREET IMPROVEMENTS

GM Contracting, Inc. was the general contractor on this project. The project consisted of approx. 6,500 LF of 6″ & 10″ watermain, 4,400 LF of 8″ & 12″ sanitary sewer and 3,000 LF of 12″, 15″ & 18″ storm sewer. New water and sewer services were also included in this project.
Location: City of Lakefield

CITY OF FOREST CITY IA – 2011 SANITARY SEWER EXTENSION

GM Contracting, Inc. was the general contractor on this project. The project consisted of approx. 1,100 LF of open cut and 5,300 LF of directional drill. New sewer services and manholes were also included in this project.
Location: City of Forest City IA

City of Dayton IA – 2010 Water Main Improvements

This was a water main project that GM Contracting was the general contractor. It consisted of approx 6400 LF of 6″ and 8″ water main replacement via trenchless methods throughout the town. Water main and service connections were also included in this project along with various valve replacements.
Location: Dayton IA

City of Ormsby – 2010 Sewer Improvements

This was a sewer project that Kuechle Underground was the general contractor on. We were hired to install approx 10,000 LF of 4″ force main and two 8″ gravity sewer lines via trenchless methods.
Location: Ormsby

City of Wilmont – 2010 Water Main Improvements

This was a water main project that GM Contracting was the general contractor. It consisted of approx 4200 LF of 6″ water main replacement via trenchless methods throughout the town. Water main and service connections were also included in this project.
Location: Wilmont

City of Rockford – TH 55 Sanitary Sewer & Watermain Improvements

This was a water and sewer replacement project that utilized open cut, directional drilling and pipe bursting. Approx 600 LF of 12″ watermain was pipe burst on this project. The existing watermain was cast iron pipe and was replaced with HDPE.
Location: Rockford

City of Nicollet – Nicollet Street & Alley

GM Contracting was a subcontractor on this project which consisted of pipe bursting approx 1600 LF of 8″ gravity sewer, reconnecting services and installing new manholes. The existing sewer was 8″ clay and was replaced with HDPE.
Location: Nicollet

City of St James – Storm Sewer Improvements

This project consisted of pipe bursting approx 1600 LF of 12″ storm sewer, installing new manholes and connecting to the existing storm sewers. The existing storm sewer was PVC, HDPE & concrete and was all replaced with HDPE.
Location: St James

City of Garfield – Sanitary Forcemain & Lift Station

Installation of lift station with air release assembly, air release valve and vault valve. Also approx 3,600 LF of 4″ PVC forcemain installed trenchless.
Location: Garfield

City of Spirit Lake IA – East Lake Industrial Park

Installed approx 900 LF of 8″ PVC sanitary sewer main and 4,200 LF of 12″ PVC watermain.
Location: Spirit Lake IA

City of Wells – CSAH 62 Reconstruction

Installed approx 3,500 LF of PVC sanitary sewer, 3,600 LF PVC watermain by open cut, and 1,100 LF of directional drill. New sewer services and manholes were also included in this project along with full concrete street restoration.
Location: Wells

City of Litchfield – Sanitary Sewer Improvements

Installed approx 2,300 LF of sewer pipe and 1,800 LF of watermain by open cut and directionally drilled 9,000 LF of 2-18″ sanitary forcemain. Included the installation of lift station
Location: Litchfield

City of Minnetrista – County Road 151 & 19 Trunk Watermain

Installed approx 4,600 LF of 12-16″ fusible PVC watermain directionally drilled along with connections.
Location: Minnetrista

City of Elk River – Twin Lake Road Watermain

Installed approx 2,600 LF of 12″ watermain via directional drilling. Water connections were also included with this project.
Location: Elk River

City of Lake Elmo – Lake Elmo Avenue Watermain Improvements

Installed approx 13,000 LF of 16″ trenchless watermain and approx 700 LF of 6″ & 16″ DIP watermain (open cut).
Location: Lake Elmo

CITY OF LAKE CRYSTAL – INDUSTRIAL PARK LIFT STATION PROJECT

Industrial Park Lift Station Project
Location: City of Lake Crystal

CITY OF ORONO

GM Contracting, Inc. was the general contractor on this project which consisted of pipe reaming and upsizing 1,500 LF of an existing 8″ clay and truss pipe sewer main to a 14″ HDPE sewer main. Manhole sealing, bypasing and sewer service installation also was done.
Location: City of Orono

CITY OF ALGONA IA – NEW WATER MAIN – GARFIELD & CHURCH ST

GM Contracting, Inc. was the general contractor on this project. The project was directional drilled with approx. 1,900 LF of 6″ PVC pipe. It also included water service hookups
Location: City of Algona IA

CITY OF FRIDLEY

GM Contracting, Inc. was the general contractor on this project which consisted of installing approx 6000 LF of 6″-14″ watermain and storm sewer via directional drilling. Water connections and storm sewer service connections were also included with this project.
Location: Fridley

City of Coon Rapids

This project was a pipe bursting and CIPP lining project throughout the City of Coon Rapids. GM Contracting was a subcontractor and was called in by Insituform because the previous pipe bursting company could not complete the project. GM Contracting bursted approx 900 FT of 8″ sewer along with making connections, repairing manholes, and connecting services.
Location: Coon Rapids

City of Eagle Lake – 2nd & 3rd Street and Parkway Ave Improvements

GM Contracting was the general contractor on this project. The project consisted of approx 6 blocks of utility and road reconstruction by both open cut and trenchless methods. New sewer and water services were also included in this project.
Location: Eagle Lake

City of Marshall – TH 59/Ontario Drive

GM Contracting has completed several projects for the City of Marshall with the most recent being TH 59/Ontario Drive Reconstruction. This project consisted of improvements including sanitary sewer and services, water main and services, minor storm sewer work, and street construction. GM Contracting was the general contractor on this and many of the other projects done in Marshall but has also done subcontract work in town.
Location: Marshall

City of Plymouth – Four Seasons Mall – Raw Watermain

This was a raw water main project that connected a new well to the existing raw water main system. Work consisted of approx 3,000 LF of 14″ pipe of which was directional drilled, along with connections and restoration. GM Contracting was the gerenal contractor on this project.
Location: Plymouth

City of Kandiyohi – Sanitary Sewer – Wastewater Regionalization with GLSSWD

This was a sewer force main project with work consisting of approx 30,400 LF of 8″ pipe and 500 LF of 20″ steel casing with 8″ PVC directional drilled. GM Contracting was sub-contractor on this project.
Location: Kandiyohi

City of Roseville – Watermain Replacement – Churchill St & Oxford St

This was a water main replacement of approx 3,000 LF of 6″ water main and approx 9,300 LF of water main services directional drilled. Work also included connecting water main to 70 houses. GM Contracting was the general contractor.
Location: Roseville

City of Harrisburg SD – Phase II Force Main

This was a force main project that connected the City of Harrisburg to the Sioux Falls sanitary sewer system. Kempf Construction was the general contractor on this project and hired GM Contracintg to directional drill a portion of the force main. The force main was 16″ fusible PVC pipe.
Location: Harrisburg SD

Grant Street Watermain Improvements

GM Contracting was a subcontractor on this project.  GM Contracting’s portion of this project included pipe bursting approx. 400LF of 6” watermain

Location: Fairmont, MN

City of Chanhassen – Well #4 Raw Watermain

This was a raw water main project that connected two new wells to the water treatment plant. Work consisted of approx 3500 LF of pipe ranging from 4″-30″ both directional drilled and open cut. Connections and restoration were also included. GM Contracting was the general contracor.
Location: Chanhassen

Kandiyohi County – Lake Florida

This is a sewer forcemain project connecting all the homes around the lake. There is approx. 50,000 LF of pipe on this project, 185 individual grinder stations, and 2 main lift stations. All the pipe and grinder stations are installed and connections are now being made to the homes.
Location: Lake Florida

City of Woden IA – Division 2 Collection System

Installed approx 3,800 LF of 4″ trenchless PVC watermain with watermain connections, 21,500 LF of 1-4″ trenchless PVC pressure sewer, 2,400 LF of 4″ PVC gravity service. Project included installing and connecting to 146 effluent pump system septic tanks.
Location: Woden IA